Up-to-date information about all ongoing and planned work

Please update this list regularly! this will help all of us to keep a better overview.

Logbook

Changed:
<
<
  • 12-13.06.2011
>
>
  • 12-13.07.2011
 
    • Fixing FEE on P1S4, re-cabling trigger cables, POF (CS, TH, AT)
    • Finished low voltage regulation S3, S6 (CS, AT)

  • 14.07.2011
    • fixed trigger distributor of P1S3, P1S6 (temporary solution because sectors not in final position),(AT)
Added:
>
>
    • fixed shaky trigger connector on P1S3 (AT)
 
Changed:
<
<

Possible to do list

>
>

List of possible works in view of the next beam time

 

Plane I:
Line: 30 to 37
  - check that the FEE is OK (standard tests)

Sector 6 (already on the main frame)
Added:
>
>
  - check that the FEE is OK (standard tests)
Deleted:
<
<
- check trigger distribution of P1
 

Plane II
Line: 54 to 63
  Lab work:

recover motherboards and/or OEPBs
Changed:
<
<
At the moment we have 40 spare MBs but only few OEPBs (boards). There is a working setup in the lab and one can use itin order to debug/repair these boards.
>
>
At the moment we have 40 spare MBs but only few OEPBs (<10 boards). There is a working setup in the lab and one can use in order to debug/repair these boards.
 
Deleted:
<
<
Trigger cabling temporary trigger cable done on plane I. Temporary because not in the final position.
 

 