Difference: MDCUpgradeLogBook (1 vs. 24)

Revision 24
01 Jan 2010 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 90 to 90
 
    • chambers 2, 4 and 6 moved to RICH tent
    • Logged serial numbers of three chambers
  • 18.11.2009
Changed:
<
<
    • Finished testing off all six chambers of plane II
>
>
    • Finished testing off all six chambers of plane II (Jörn, Kathrin, Jan)
 
  • 07.12.2009
  • 09.12.2009
Line: 98 to 98
 
  • 10.12.2009
    • MDC Plane 1 arrived
  • 11.12.2009
Changed:
<
<
    • Reworked CMS cables sector 3 & 5 and plane 2
>
>
    • Reworked CMS cables sector 3 & 5 and plane 2 (Gosia, Erwin)
 
    • Finished cables on sector 3 (plane 3/4)
Changed:
<
<
    • Tested FanPW3 / found to be ok. Rest of boards can be produced
>
>
    • Tested FanPW3 / found to be ok. Rest of boards can be produced (Paul, Erik, Jan)
  • 22.12.2009
    • Finished cabling on long sides of plane 2 (Kathrin, Jan)
    • Installed missing OEP / Replaced broken OEP on plane 2 (Kathrin, Jan)
 

Upcoming

  • Gosia and Tingting are available for 3 weeks (in total) in january, in the 1st, 3rd and 4th week
Line: 109 to 111
 

Changed:
<
<
>
>
 

Other Tasks

  • 48V power distribution
Revision 23
11 Dec 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 91 to 91
 
    • Logged serial numbers of three chambers
  • 18.11.2009
    • Finished testing off all six chambers of plane II
Changed:
<
<
    • Ready to be mounted back!
>
>
  • 07.12.2009
  • 09.12.2009
    • CMS cables found to be not crimped correctly - to be reworked!
  • 10.12.2009
    • MDC Plane 1 arrived
  • 11.12.2009
    • Reworked CMS cables sector 3 & 5 and plane 2
    • Finished cables on sector 3 (plane 3/4)
    • Tested FanPW3 / found to be ok. Rest of boards can be produced
 

Upcoming

Changed:
<
<
  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
    • 13.10. arrival of chamber, mounting of MDC-III and MDC-IV
    • 14.10. upgrade of chamber
    • 15. - 16.10. test of electronics
    • 21.10. mounting to mainframe
  • 19.10. - 21.10. : Break in MDC works in cave due to RPC installation
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 02.11. : MDC-II Upgrade starting

Tasks for the next days (2009-11-02)

  • Check cutting of optical cables in mainframe
  • finish cabling of sector 5 (cut optical wires, mount connector)
  • finish equipping sector 2

Fan PW v3

  • PCB ordered, will arrive around 10.11.
  • then sent to company to mount components
  • will be ready in december
>
>
  • Gosia and Tingting are available for 3 weeks (in total) in january, in the 1st, 3rd and 4th week
  • Big coordinated effort in january to test all chambers of plane 3/4, finish upgrading plane 1, preparing all cables in mainframe for plane 1/2...
 

Revision 22
18 Nov 2009 - Main.JoernWuestenfeld
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 85 to 85
 
    • chambers 1, 3 and 5 of MDC II moved to Rich tent
    • Logged serial numbers of three chambers
    • Decided on strategy for placing FanPW and Power Cables
Added:
>
>
  • 12.11.2009
    • chambers 1, 3 and 5 of MDC II moved back to frustum
    • chambers 2, 4 and 6 moved to RICH tent
    • Logged serial numbers of three chambers
  • 18.11.2009
    • Finished testing off all six chambers of plane II
    • Ready to be mounted back!
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 21
05 Nov 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 83 to 83
 
    • Started preparing power cables (Sasha)
  • 05.11.2009
    • chambers 1, 3 and 5 of MDC II moved to Rich tent
Added:
>
>
    • Logged serial numbers of three chambers
    • Decided on strategy for placing FanPW and Power Cables
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 20
05 Nov 2009 - Main.KathrinGoebel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 81 to 81
 
    • Labelled optical cables for sector 2 (Gosia, Torsten)
    • Equipped both long sides of sector 2
    • Started preparing power cables (Sasha)
Added:
>
>
  • 05.11.2009
    • chambers 1, 3 and 5 of MDC II moved to Rich tent
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 19
04 Nov 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 77 to 77
 
    • Labelled optical cables for sector 3 (Gosia)
    • Mounted cables and some OEP on sector 2 (Torsten, Gosia)
    • Produced OEPs (Helga)
Added:
>
>
  • 04.11.2009
    • Labelled optical cables for sector 2 (Gosia, Torsten)
    • Equipped both long sides of sector 2
    • Started preparing power cables (Sasha)
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 18
03 Nov 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 72 to 72
 
    • Cut missing power cables (Gosia)
    • Mounted connectors on power cables in mainframe (Torsten)
    • Produced OEPs (Helga)
Changed:
<
<

>
>
  • 03.11.2009
    • Removed all cables from plane 2 (Sasha, Sergey)
    • Labelled optical cables for sector 3 (Gosia)
    • Mounted cables and some OEP on sector 2 (Torsten, Gosia)
    • Produced OEPs (Helga)
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Line: 86 to 90
 

Tasks for the next days (2009-11-02)

Deleted:
<
<
  • Put numbers on optical cables for sector 3
 
  • Check cutting of optical cables in mainframe
  • finish cabling of sector 5 (cut optical wires, mount connector)
  • finish equipping sector 2
Revision 17
02 Nov 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 67 to 67
 
  • 30.10.2009
    • Noise measurement for proposed position of cables for MDC II (Kathrin)
    • mounted cables on plane 4, sector 2 right side (Gosia, Kathrin)
Added:
>
>
  • 02.11.2009
    • Started removing cables from plane 2 (Sasha, Sergey, Jan)
    • Cut missing power cables (Gosia)
    • Mounted connectors on power cables in mainframe (Torsten)
    • Produced OEPs (Helga)
 

Upcoming

Line: 80 to 85
 
  • 02.11. : MDC-II Upgrade starting
Changed:
<
<

Tasks for the next days (2009-10-29)

>
>

Tasks for the next days (2009-11-02)

 
  • Put numbers on optical cables for sector 3
Changed:
<
<
  • Produce power and optical cables for plane 3, right side
  • Put power connectors on cables for sector 5
>
>
  • Check cutting of optical cables in mainframe
  • finish cabling of sector 5 (cut optical wires, mount connector)
 
  • finish equipping sector 2
Deleted:
<
<
  • remove protection from power conectors on third fanpw2
 

Fan PW v3

Changed:
<
<
  • PCB ordered, will arrive around 30.10.
>
>
  • PCB ordered, will arrive around 10.11.
 
  • then sent to company to mount components
  • will be ready in december
Revision 16
01 Nov 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 59 to 59
 
    • Installed proper grounding for sector 4
  • 28.10.2009
    • Tested 34 OEP (Erik)
Changed:
<
<
    • Adjusted FanPW2 on sector 4 (Kathrin, Jan)
>
>
    • Adjusted FanPW2 on sector 4 (Kathrin, Jan)
 
    • worked on analysis scripts (Kathrin, Jan)
  • 29.10.2009
    • Installed OEP and cables on second half of sector 5 (Erwin, Gosia)
    • Produced optical cables for one sector plane 3&4 (Gosia)
Added:
>
>
  • 30.10.2009
    • Noise measurement for proposed position of cables for MDC II (Kathrin)
    • mounted cables on plane 4, sector 2 right side (Gosia, Kathrin)
 

Upcoming

Line: 74 to 77
 
    • 21.10. mounting to mainframe
  • 19.10. - 21.10. : Break in MDC works in cave due to RPC installation
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
Changed:
<
<
  • 01.11. : MDC-II Upgrade starting
>
>
  • 02.11. : MDC-II Upgrade starting
 

Tasks for the next days (2009-10-29)

  • Put numbers on optical cables for sector 3
  • Produce power and optical cables for plane 3, right side
  • Put power connectors on cables for sector 5
Changed:
<
<
  • start equipping sector 2
>
>
  • finish equipping sector 2
  • remove protection from power conectors on third fanpw2
 

Fan PW v3

Line: 100 to 104
 
  • 15.11. (?) 32 boards for sector 1 (3&4)
  • (?) 16 boards for sector 5 plane 3
Deleted:
<
<
-- JanMichel - 28 Oct 2009
 

Other Tasks

  • 48V power distribution
Revision 15
29 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 61 to 61
 
    • Tested 34 OEP (Erik)
    • Adjusted FanPW2 on sector 4 (Kathrin, Jan)
    • worked on analysis scripts (Kathrin, Jan)
Added:
>
>
  • 29.10.2009
    • Installed OEP and cables on second half of sector 5 (Erwin, Gosia)
    • Produced optical cables for one sector plane 3&4 (Gosia)
 

Upcoming

Line: 73 to 76
 
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 01.11. : MDC-II Upgrade starting
Added:
>
>

Tasks for the next days (2009-10-29)

  • Put numbers on optical cables for sector 3
  • Produce power and optical cables for plane 3, right side
  • Put power connectors on cables for sector 5
  • start equipping sector 2
 

Fan PW v3

  • PCB ordered, will arrive around 30.10.
  • then sent to company to mount components
Line: 81 to 92
 

Needed OEPs

  • 09.10. 50 boards for sector 4, one side of sector 3 & 5, plane 3 and 4
  • 14.10. 32 boards for sector 6, plane 3 and 4
Changed:
<
<
  • 30.10. 20 boards for half of sector 5 (3&4)
>
>
  • 29.10. 20 boards for half of sector 5 (3&4)
 
  • 30.10. 10 boards for half of sector 3 plane 4
Added:
>
>
  • 30.10. 32 boards for sector 2 (3&4)
 
  • 01.11. 96 boards for plane 2
  • 15.11. (?) 84 boards for plane 1
  • 15.11. (?) 32 boards for sector 1 (3&4)
Deleted:
<
<
  • 15.11. (?) 32 boards for sector 2 (3&4)
 
  • (?) 16 boards for sector 5 plane 3

-- JanMichel - 28 Oct 2009
Revision 14
28 Oct 2009 - Main.MichaelTraxler
Line: 1 to 1
 
META TOPICPARENT name="MDCUpgradeInstallation"
Up-to-date information about all ongoing and planned work
Line: 57 to 57
 
  • 23.10.2009
    • Tested about 60 OEP (Erik, Paul)
    • Installed proper grounding for sector 4
Added:
>
>
  • 28.10.2009
    • Tested 34 OEP (Erik)
    • Adjusted FanPW2 on sector 4 (Kathrin, Jan)
    • worked on analysis scripts (Kathrin, Jan)
 

Upcoming

Line: 77 to 81
 

Needed OEPs

  • 09.10. 50 boards for sector 4, one side of sector 3 & 5, plane 3 and 4
  • 14.10. 32 boards for sector 6, plane 3 and 4
Added:
>
>
  • 30.10. 20 boards for half of sector 5 (3&4)
  • 30.10. 10 boards for half of sector 3 plane 4
 
  • 01.11. 96 boards for plane 2
  • 15.11. (?) 84 boards for plane 1
  • 15.11. (?) 32 boards for sector 1 (3&4)
  • 15.11. (?) 32 boards for sector 2 (3&4)
Deleted:
<
<
  • 15.11. (?) 20 boards for half of sector 3 (3&4)
 
  • (?) 16 boards for sector 5 plane 3
Deleted:
<
<
  • 15.11. (?) 10 boards for half of sector 5 plane 4
 
Added:
>
>
-- JanMichel - 28 Oct 2009
 

Other Tasks

  • 48V power distribution
Deleted:
<
<

-- JanMichel - 12 Oct 2009
Revision 13
26 Oct 2009 - Main.JanMichel
Line: 1 to 1
Changed:
<
<
META TOPICPARENT name="DaqUpgradeMDCOverview"
>
>
META TOPICPARENT name="MDCUpgradeInstallation"
  Up-to-date information about all ongoing and planned work
Revision 12
23 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 52 to 52
 
  • 20.10.2009
    • Test of threshold settings and internal calibration on sector 6 -> all boards behave normal (Christian, Jan)
    • Found quite high noise on all voltages, needs further investigation
Added:
>
>
  • 21.10.2009
    • Installation of sector 6
  • 23.10.2009
    • Tested about 60 OEP (Erik, Paul)
    • Installed proper grounding for sector 4
 

Upcoming

Revision 11
20 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 64 to 64
 
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 01.11. : MDC-II Upgrade starting
Added:
>
>

Fan PW v3

  • PCB ordered, will arrive around 30.10.
  • then sent to company to mount components
  • will be ready in december
 

Needed OEPs

  • 09.10. 50 boards for sector 4, one side of sector 3 & 5, plane 3 and 4
  • 14.10. 32 boards for sector 6, plane 3 and 4
Revision 10
20 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 46 to 46
 
    • connected both chambers of sector 6 to MDC AddOn (Tingting, Kathrin, Jan)
    • Basic communication and readout tests succesfull (Tingting, Kathrin, Jan)
    • Connected sector 4, plane 3 to power and AddOn (Sergey, Jan) - will be used by Sergey for software tests
Added:
>
>
  • 19.10.2009
    • Noise tests with sector 4
    • cosmetic repairs on sector 6
  • 20.10.2009
    • Test of threshold settings and internal calibration on sector 6 -> all boards behave normal (Christian, Jan)
    • Found quite high noise on all voltages, needs further investigation

 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 9
15 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 42 to 42
 
    • tested 21 OEP, produced 43 OEP (Jan / Helga, Albrecht)
    • build rack with fans for three Optical AddOns (Jan)
    • glued final optical connector sector 4 (Torsten)
Added:
>
>
  • 15.10.2009
    • connected both chambers of sector 6 to MDC AddOn (Tingting, Kathrin, Jan)
    • Basic communication and readout tests succesfull (Tingting, Kathrin, Jan)
    • Connected sector 4, plane 3 to power and AddOn (Sergey, Jan) - will be used by Sergey for software tests
 

Upcoming

  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
Revision 8
14 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 34 to 34
 
    • Tested 30 OEP (Sergey, Jan)
    • Prepared chambers to move in sector 4 (Kathrin, Tingting, Jan)
    • Rasnik connector box moved (Torsten + ?)
Added:
>
>
  • 14.10.2009
    • Mounted both chambers (sector 6) together (Torsten, Erwin, ?)
    • Installed all cables (Kathrin, Tingting, Erwin, Jan)
    • Installed all OEP (Kathrin, Tingting, Jan)
    • Logged all available serial numbers (Kathrin, Tingting, Erwin, Jan)
    • tested 21 OEP, produced 43 OEP (Jan / Helga, Albrecht)
    • build rack with fans for three Optical AddOns (Jan)
    • glued final optical connector sector 4 (Torsten)
 

Upcoming

Changed:
<
<
  • 13.10. - 16.10. : Installation and Upgrade of MDC sector 6
>
>
  • 13.10. - 21.10. : Installation and Upgrade of MDC sector 6
 
    • 13.10. arrival of chamber, mounting of MDC-III and MDC-IV
Changed:
<
<
    • 14.10. - 15.10. upgrade of chamber
    • 16.10. mounting to mainframe
>
>
    • 14.10. upgrade of chamber
    • 15. - 16.10. test of electronics
    • 21.10. mounting to mainframe
 
  • 19.10. - 21.10. : Break in MDC works in cave due to RPC installation
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 01.11. : MDC-II Upgrade starting
Revision 7
14 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 44 to 44
 
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 01.11. : MDC-II Upgrade starting
Added:
>
>

Needed OEPs

  • 09.10. 50 boards for sector 4, one side of sector 3 & 5, plane 3 and 4
  • 14.10. 32 boards for sector 6, plane 3 and 4
  • 01.11. 96 boards for plane 2
  • 15.11. (?) 84 boards for plane 1
  • 15.11. (?) 32 boards for sector 1 (3&4)
  • 15.11. (?) 32 boards for sector 2 (3&4)
  • 15.11. (?) 20 boards for half of sector 3 (3&4)
  • (?) 16 boards for sector 5 plane 3
  • 15.11. (?) 10 boards for half of sector 5 plane 4

 

Other Tasks

  • 48V power distribution
Revision 6
12 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 36 to 36
 
    • Rasnik connector box moved (Torsten + ?)

Upcoming

Changed:
<
<
  • until 14.10. : At least 32 OEPs must be programmed and tested for sector 6
  • until 14.10. : 2 final optical connectors needed
  • 12.10. - 16.10. : Installation and Upgrade of MDC sector 6
>
>
  • 13.10. - 16.10. : Installation and Upgrade of MDC sector 6
    • 13.10. arrival of chamber, mounting of MDC-III and MDC-IV
    • 14.10. - 15.10. upgrade of chamber
    • 16.10. mounting to mainframe
 
  • 19.10. - 21.10. : Break in MDC works in cave due to RPC installation
Changed:
<
<
>
>
  • 26.11. : Preparation for upgrade of upper sectors MDC-III/IV(scaffolding, etc.)
  • 01.11. : MDC-II Upgrade starting
 

Other Tasks

  • 48V power distribution
Revision 5
12 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 9 to 9
 

Logbook

  • 29.09.2009
Changed:
<
<
    • Finished low voltage distribution for sector 3 (3&4)
    • Power Supplies installed
    • Connected sector 3 with a temporary "final" test setup
>
>
    • Finished low voltage distribution for sector 3 plane 3&4 (Torsten)
    • Power Supplies installed (Torsten)
    • Connected sector 3 with a temporary "final" test setup (Kathrin, Jan)
 
  • 02.10.2009
Changed:
<
<
    • Installation of main slow control switch
>
>
    • Installation of main slow control network switch (Sergey, Jan)
 
  • 07.10.2009
Changed:
<
<
    • Torsten and Jan labeled optical cables for sector 6
    • Network (VLAN & GSI network) connection on both mdc mounting places
    • Two additional (3 in total) FanPW v2 adjusted and tested
    • Automatic OEP test script almost finished
>
>
    • Labeled optical cables for sector 6 (Torsten, Jan)
    • Network (VLAN & GSI network) connection on both mdc mounting places (Sergey, Jan)
    • Two additional (3 in total) FanPW v2 adjusted and tested (Jan)
    • Automatic OEP test script almost finished (Sergey)
 
  • 08.10.2009
    • 15 OEP tested (Sergey)
  • 09.10.2009
Changed:
<
<
    • Tested 15 more OEP, found some broken ones
    • Enabled write protection on all 30 OEP finished
    • Labelled and Cut optical fibres for sector 5
    • Cut all power cables for one sector plane 3&4
    • Cut optical cables for two full sectors plane 3&4
>
>
    • Tested 15 more OEP, found some broken ones (Jan)
    • Enabled write protection on all 30 OEP finished (Cahit, Jan)
    • Labelled and Cut optical fibres for sector 5 (Kathrin, Jan)
    • Cut all power cables for one sector plane 3&4 (Kathrin, Jan)
    • Cut optical cables for two full sectors plane 3&4 (Kathrin, Jan)
  • 12.10.2009
    • Cut and tested power cables for two full sectors (Linda, Kathrin, Jan)
    • Installed 50 OEPs: Sector 4 Plane 3 & 4; one long side of sector 3 & 5, plane 3 & 4 (Tingting, Kathrin, Jan)
    • Cut all cables belonging to sector 4 plane 3&4 (Kathrin, Jan)
    • Tested 30 OEP (Sergey, Jan)
    • Prepared chambers to move in sector 4 (Kathrin, Tingting, Jan)
    • Rasnik connector box moved (Torsten + ?)
 

Upcoming

  • until 14.10. : At least 32 OEPs must be programmed and tested for sector 6
Line: 37 to 44
 

Other Tasks

  • 48V power distribution
Deleted:
<
<
  • finish upgrade of sector 3
  • Move Rasnik cables and connectors as necesssary
 
Changed:
<
<
-- JanMichel - 07 Oct 2009
>
>
-- JanMichel - 12 Oct 2009
 
Revision 4
09 Oct 2009 - Main.MichaelTraxler
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 19 to 19
 
    • Network (VLAN & GSI network) connection on both mdc mounting places
    • Two additional (3 in total) FanPW v2 adjusted and tested
    • Automatic OEP test script almost finished
Added:
>
>
  • 08.10.2009
    • 15 OEP tested (Sergey)
  • 09.10.2009
    • Tested 15 more OEP, found some broken ones
    • Enabled write protection on all 30 OEP finished
    • Labelled and Cut optical fibres for sector 5
    • Cut all power cables for one sector plane 3&4
    • Cut optical cables for two full sectors plane 3&4
 

Upcoming

  • until 14.10. : At least 32 OEPs must be programmed and tested for sector 6
Revision 3
08 Oct 2009 - Main.JanMichel
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Line: 30 to 30
 

Other Tasks

  • 48V power distribution
  • finish upgrade of sector 3
Added:
>
>
  • Move Rasnik cables and connectors as necesssary
 

-- JanMichel - 07 Oct 2009
Revision 2
07 Oct 2009 - Main.MichaelTraxler
Line: 1 to 1
 
META TOPICPARENT name="DaqUpgradeMDCOverview"
Up-to-date information about all ongoing and planned work
Changed:
<
<
Please update this list with regularly! I think this will help all of us to keep a better overview of the whole project.
>
>
Please update this list regularly! I think this will help all of us to keep a better overview of the whole project.
 

 