Up-to-date information about all ongoing and planned work
Please update this list regularly! this will help all of us to keep a better overview.
Logbook
- 12-13.07.2011
- Fixing FEE on P1S4, re-cabling trigger cables, POF (CS, TH, AT)
- Finished low voltage regulation S3, S6 (CS, AT)
- 14.07.2011
- fixed trigger distributor of P1S3, P1S6 (temporary solution because sectors not in final position),(AT)
- fixed shaky trigger connector on P1S3 (AT)
List of possible works in view of the next beam time
Plane I:
Sector 4: (in the RICH tent)
- regulate the voltages after mounted on the main frame
- check that the FEE is OK (standard tests)
- check 0x201b (nr 389) trigger cable not connected most probably
Sector 5: (conditioned, on the table now 14.07.11)
- regulate the voltages
- check that the FEE is OK (standard tests)
Sector 3 (already on the main frame)
- check that the FEE is OK (standard tests)
Sector 6 (already on the main frame)
- check that the FEE is OK (standard tests)
Plane II
OK. some voltages are not regulated because not accessible. If possible check them.
Plane III
- Sector 2 and sector 4 are disconnected.
We should connect to the common DAQ and do the usual check on the FEE.
Re-check the voltages (already checked but not on the main frame with the final ground)
- Board 2309 from time to time does not work properly.
Plane IV
- Sector 2 and sector 4 are disconnected. We should connect to the common DAQ and do the usual check on the FEE.
Re-check the voltages (already checked but not on the main frame with the final ground)
- Board 2350, 2353 don't work properly
Lab work:
recover motherboards and/or OEPBs
At the moment we have 40 spare MBs but only few OEPBs (<10 boards). There is a working setup in the lab and one can use in order to debug/repair these boards.
--
AttilioTarantola - 14 Jul 2011