Open Tasks
Tasks currently on our agenda:
- Remove obsolete cables - still a topic (Everybody who is familiar with the old setup)
- Install temperature sensors for RICH power supplies
- Re-Install MDC Analog Out connection to Counting House (Erwin)
- Add fans where missing
- Install trigger cables TOF-MDC34
- Install trigger cables for RPC (Alberto)
- Install trigger cables for Forward Wall
- Adjust all FanPW to final settings
- Connect power for RPC switches
- Install RPC Hadcon (Alberto)
- MDC - what is missing?
Logbook
18.01.2010
- Put cables and filters on 10 more new fans (Joern, Jan)
- Prepare RPC / Shower trigger cables (Gosia)
- Lay 48V distribution for TRBs MDC12 RICH (Torsten)
- Lay 48V distribution for TRBs left front (Torsten)
- Lay 48V distribution for TRBs right front (Torsten)
- Lay Optical cables left front corner (Jan)
- Finish TOF TRB stacks (Joern, Jan)
- Finish MDC1 sector 4 cables (Gosia, Joern)
- Find and install available network switches (Sergey)
19.01.2010
- removed power cables for RICH (Joern, Khaled, Jan)
- Prepare more 50cm power cables (Khaled, Gosia, Joern)
- Add filters for Fans where missing (Joern)
- Lay 48V distribution for RPC TRB (Torsten)
- Lay 48V distribution for RPC (Torsten)
- Prepared optical cables for MDC 1/2 (Gosia, Joern, Torsten, Jan)
- Loaded new kernels on many trbs (Sergey)
20.01.2010
- Made list of available temperature sensors for MDC1/2 (Khaled)
- Soldered new temperature sensors (Erik)
- Removed RICH power cable to tent (Erwin)
- Installed front left and rear right TRB stacks (Andreas)
- Installed final Ethernet setup for all three corners of the mainframe (Sergey, Jan)
- Changed stack for CTS (Jan)
- Continued tests for MDC (Gosia, Joern)
- Fixed some mistakes on sector 3 plane 3/4 (Gosia, Erwin)
22.01.2010
- Layed all optical cables for rear right, front right corner and MDC1/2 / RICH to optical switches, Ethernet switches and CTS (Joern, Erwin, Jan)
- Installed TRB mountings (Andreas)
- Mounted TRB stacks (Joern, Andreas, Jan)
- Soldered trigger distributor boards (Gabi)
- Soldered all temperature sensors for MDC plane 3&4 (Erik, Gosia)
- Mounted trigger distributor on TRB stacks (Gosia)
- Removed MDC Analog Out Cables between Patch panels - has to be redone in a better way (Joern, Erwin)
- Removed LEMO cables on MDC rack
26.01.2010
- Lay 48V distribution for TRBs right rear (Torsten)
- Build holding for optical switches (Andreas)
- Installed and connected optical switches for MDC1/2 & RICH (Jan)
- Changed RPC stacks on sector 3 & 5 to final setup (Yurek, Jan)
- Equipped one more RPC stack (Marek, Jan)
- Prepared power cables for Trigger distributor board (Jan)
27.01.2010
- Prepared two new trigger cables for RPC (Kathrin)
- Change power supply for RPC to final setup (Torsten, Jan)
28.01.2010
- The last three stacks prepared for RPC (Marek, Sergey)
29.01.2010
- Prepared six TRB stacks for TOF with Power distributor (Erik)
- Installed two network switches in rear right corner, including cables (Jan)
- Labeled most of RPC cables individually (Kathrin)
- Layed trigger cable (17pair) from CTS to both TOF/MDC34 and RPC/Shower / corner of mainframe (Erwin, Jan)
- Prepared more 50cm 48V cables (Paul)
- Put RJ45 connectors on PCB for temperature sensors (Paul, Erik)
- Started removing temporary RPC setup (Jan)
01.02.2010
- Removed all temporary RPC setups
- Uninstalled LV power supplies for making changes
- Put cables for TOF on sector 3
- Prepared cables for RPC / Shower to be put into new cable chains.
03.02.2010
- Three stacks of RPC TRBs successfully tested (CTS, old HUB, readout) and ready for mounting (Marek, Sergey)
09.02.2010
- Installed cable guide on rear corners (Torsten, Andreas, Jan)
- Continued with TOF cables (Erwin)
18.02.2010
- Two stacks with TRBs for RPC built and tested (CTS, old HUB, readout) and ready for mounting (Marek, Sergey)
19.02.2010
- Four TRBs for TOF tested (CTS, old HUB, readout) and ready for mounting (Marek, Sergey)
22.02.2010 (and before)
- Install new cable guides to RPC/Shower
- Soldered temperature sensor hub boards
- Soldered CTS trigger fanout boards
- Finished testing & labelling half of temperature sensors for MDC 3/4
- Lay all DAQ cables to each RPC/Shower sector (1x trigger, 6x optical cable, 1x Ethernet, 1x Temp.Sens. 2x CAN)
07.05.2010
- Installed Forward Wall Hub
- Changed trigger setup according to Michael's mail
--
JanMichel - 29 Jan 2010