Up-to-date information about all ongoing and planned work

Please update this list regularly! I think this will help all of us to keep a better overview of the whole project.

Logbook

  • 29.09.2009
    • Finished low voltage distribution for sector 3 plane 3&4 (Torsten)
    • Power Supplies installed (Torsten)
    • Connected sector 3 with a temporary "final" test setup (Kathrin, Jan)
  • 02.10.2009
    • Installation of main slow control network switch (Sergey, Jan)
  • 07.10.2009
    • Labeled optical cables for sector 6 (Torsten, Jan)
    • Network (VLAN & GSI network) connection on both mdc mounting places (Sergey, Jan)
    • Two additional (3 in total) FanPW v2 adjusted and tested (Jan)
    • Automatic OEP test script almost finished (Sergey)
  • 08.10.2009
    • 15 OEP tested (Sergey)
  • 09.10.2009
    • Tested 15 more OEP, found some broken ones (Jan)
    • Enabled write protection on all 30 OEP finished (Cahit, Jan)
    • Labelled and Cut optical fibres for sector 5 (Kathrin, Jan)
    • Cut all power cables for one sector plane 3&4 (Kathrin, Jan)
    • Cut optical cables for two full sectors plane 3&4 (Kathrin, Jan)
  • 12.10.2009
    • Cut and tested power cables for two full sectors (Linda, Kathrin, Jan)
    • Installed 50 OEPs: Sector 4 Plane 3 & 4; one long side of sector 3 & 5, plane 3 & 4 (Tingting, Kathrin, Jan)
    • Cut all cables belonging to sector 4 plane 3&4 (Kathrin, Jan)
    • Tested 30 OEP (Sergey, Jan)
    • Prepared chambers to move in sector 4 (Kathrin, Tingting, Jan)
    • Rasnik connector box moved (Torsten + ?)
  • 14.10.2009
    • Mounted both chambers (sector 6) together (Torsten, Erwin, ?)
    • Installed all cables (Kathrin, Tingting, Erwin, Jan)
    • Installed all OEP (Kathrin, Tingting, Jan)
    • Logged all available serial numbers (Kathrin, Tingting, Erwin, Jan)
    • tested 21 OEP, produced 43 OEP (Jan / Helga, Albrecht)
    • build rack with fans for three Optical AddOns (Jan)
    • glued final optical connector sector 4 (Torsten)
  • 15.10.2009
    • connected both chambers of sector 6 to MDC AddOn (Tingting, Kathrin, Jan)
    • Basic communication and readout tests succesfull (Tingting, Kathrin, Jan)
    • Connected sector 4, plane 3 to power and AddOn (Sergey, Jan) - will be used by Sergey for software tests
  • 19.10.2009
    • Noise tests with sector 4
    • cosmetic repairs on sector 6
  • 20.10.2009
    • Test of threshold settings and internal calibration on sector 6 -> all boards behave normal (Christian, Jan)
    • Found quite high noise on all voltages, needs further investigation
  • 21.10.2009
    • Installation of sector 6
  • 23.10.2009
    • Tested about 60 OEP (Erik, Paul)
    • Installed proper grounding for sector 4
  • 28.10.2009
    • Tested 34 OEP (Erik)
    • Adjusted FanPW2 on sector 4 (Kathrin, Jan)
    • worked on analysis scripts (Kathrin, Jan)
  • 29.10.2009
    • Installed OEP and cables on second half of sector 5 (Erwin, Gosia)
    • Produced optical cables for one sector plane 3&4 (Gosia)
  • 30.10.2009
    • Noise measurement for proposed position of cables for MDC II (Kathrin)
    • mounted cables on plane 4, sector 2 right side (Gosia, Kathrin)
  • 02.11.2009
    • Started removing cables from plane 2 (Sasha, Sergey, Jan)
    • Cut missing power cables (Gosia)
    • Mounted connectors on power cables in mainframe (Torsten)
    • Produced OEPs (Helga)
  • 03.11.2009
    • Removed all cables from plane 2 (Sasha, Sergey)
    • Labelled optical cables for sector 3 (Gosia)
    • Mounted cables and some OEP on sector 2 (Torsten, Gosia)
    • Produced OEPs (Helga)
  • 04.11.2009
    • Labelled optical cables for sector 2 (Gosia, Torsten)
    • Equipped both long sides of sector 2
    • Started preparing power cables (Sasha)
  • 05.11.2009
    • chambers 1, 3 and 5 of MDC II moved to Rich tent
    • Logged serial numbers of three chambers
    • Decided on strategy for placing FanPW and Power Cables
  • 12.11.2009
    • chambers 1, 3 and 5 of MDC II moved back to frustum
    • chambers 2, 4 and 6 moved to RICH tent
    • Logged serial numbers of three chambers
  • 18.11.2009
    • Finished testing off all six chambers of plane II (Jrn, Kathrin, Jan)
  • 07.12.2009
  • 09.12.2009
    • CMS cables found to be not crimped correctly - to be reworked!
  • 10.12.2009
    • MDC Plane 1 arrived
  • 11.12.2009
    • Reworked CMS cables sector 3 & 5 and plane 2 (Gosia, Erwin)
    • Finished cables on sector 3 (plane 3/4)
    • Tested FanPW3 / found to be ok. Rest of boards can be produced (Paul, Erik, Jan)
  • 22.12.2009
    • Finished cabling on long sides of plane 2 (Kathrin, Jan)
    • Installed missing OEP / Replaced broken OEP on plane 2 (Kathrin, Jan)

Upcoming

  • Gosia and Tingting are available for 3 weeks (in total) in january, in the 1st, 3rd and 4th week
  • Big coordinated effort in january to test all chambers of plane 3/4, finish upgrading plane 1, preparing all cables in mainframe for plane 1/2...

Other Tasks

  • 48V power distribution
Topic revision: r24 - 2010-01-01, JanMichel