Up-to-date information about all ongoing and planned work
Please update this list regularly! I think this will help all of us to keep a better overview of the whole project.
Logbook
- 29.09.2009
- Finished low voltage distribution for sector 3 plane 3&4 (Torsten)
- Power Supplies installed (Torsten)
- Connected sector 3 with a temporary "final" test setup (Kathrin, Jan)
- 02.10.2009
- Installation of main slow control network switch (Sergey, Jan)
- 07.10.2009
- Labeled optical cables for sector 6 (Torsten, Jan)
- Network (VLAN & GSI network) connection on both mdc mounting places (Sergey, Jan)
- Two additional (3 in total) FanPW v2 adjusted and tested (Jan)
- Automatic OEP test script almost finished (Sergey)
- 08.10.2009
- 09.10.2009
- Tested 15 more OEP, found some broken ones (Jan)
- Enabled write protection on all 30 OEP finished (Cahit, Jan)
- Labelled and Cut optical fibres for sector 5 (Kathrin, Jan)
- Cut all power cables for one sector plane 3&4 (Kathrin, Jan)
- Cut optical cables for two full sectors plane 3&4 (Kathrin, Jan)
- 12.10.2009
- Cut and tested power cables for two full sectors (Linda, Kathrin, Jan)
- Installed 50 OEPs: Sector 4 Plane 3 & 4; one long side of sector 3 & 5, plane 3 & 4 (Tingting, Kathrin, Jan)
- Cut all cables belonging to sector 4 plane 3&4 (Kathrin, Jan)
- Tested 30 OEP (Sergey, Jan)
- Prepared chambers to move in sector 4 (Kathrin, Tingting, Jan)
- Rasnik connector box moved (Torsten + ?)
- 14.10.2009
- Mounted both chambers (sector 6) together (Torsten, Erwin, ?)
- Installed all cables (Kathrin, Tingting, Erwin, Jan)
- Installed all OEP (Kathrin, Tingting, Jan)
- Logged all available serial numbers (Kathrin, Tingting, Erwin, Jan)
- tested 21 OEP, produced 43 OEP (Jan / Helga, Albrecht)
- build rack with fans for three Optical AddOns (Jan)
- glued final optical connector sector 4 (Torsten)
- 15.10.2009
- connected both chambers of sector 6 to MDC AddOn (Tingting, Kathrin, Jan)
- Basic communication and readout tests succesfull (Tingting, Kathrin, Jan)
- Connected sector 4, plane 3 to power and AddOn (Sergey, Jan) - will be used by Sergey for software tests
- 19.10.2009
- Noise tests with sector 4
- cosmetic repairs on sector 6
- 20.10.2009
- Test of threshold settings and internal calibration on sector 6 -> all boards behave normal (Christian, Jan)
- Found quite high noise on all voltages, needs further investigation
- 21.10.2009
- 23.10.2009
- Tested about 60 OEP (Erik, Paul)
- Installed proper grounding for sector 4
- 28.10.2009
- Tested 34 OEP (Erik)
- Adjusted FanPW2 on sector 4 (Kathrin, Jan)
- worked on analysis scripts (Kathrin, Jan)
- 29.10.2009
- Installed OEP and cables on second half of sector 5 (Erwin, Gosia)
- Produced optical cables for one sector plane 3&4 (Gosia)
- 30.10.2009
- Noise measurement for proposed position of cables for MDC II (Kathrin)
- mounted cables on plane 4, sector 2 right side (Gosia, Kathrin)
- 02.11.2009
- Started removing cables from plane 2 (Sasha, Sergey, Jan)
- Cut missing power cables (Gosia)
- Mounted connectors on power cables in mainframe (Torsten)
- Produced OEPs (Helga)
- 03.11.2009
- Removed all cables from plane 2 (Sasha, Sergey)
- Labelled optical cables for sector 3 (Gosia)
- Mounted cables and some OEP on sector 2 (Torsten, Gosia)
- Produced OEPs (Helga)
- 04.11.2009
- Labelled optical cables for sector 2 (Gosia, Torsten)
- Equipped both long sides of sector 2
- Started preparing power cables (Sasha)
- 05.11.2009
- chambers 1, 3 and 5 of MDC II moved to Rich tent
- Logged serial numbers of three chambers
- Decided on strategy for placing FanPW and Power Cables
- 12.11.2009
- chambers 1, 3 and 5 of MDC II moved back to frustum
- chambers 2, 4 and 6 moved to RICH tent
- Logged serial numbers of three chambers
- 18.11.2009
- Finished testing off all six chambers of plane II (Jrn, Kathrin, Jan)
- 07.12.2009
- 09.12.2009
- CMS cables found to be not crimped correctly - to be reworked!
- 10.12.2009
- 11.12.2009
- Reworked CMS cables sector 3 & 5 and plane 2 (Gosia, Erwin)
- Finished cables on sector 3 (plane 3/4)
- Tested FanPW3 / found to be ok. Rest of boards can be produced (Paul, Erik, Jan)
- 22.12.2009
- Finished cabling on long sides of plane 2 (Kathrin, Jan)
- Installed missing OEP / Replaced broken OEP on plane 2 (Kathrin, Jan)
Upcoming
- Gosia and Tingting are available for 3 weeks (in total) in january, in the 1st, 3rd and 4th week
- Big coordinated effort in january to test all chambers of plane 3/4, finish upgrading plane 1, preparing all cables in mainframe for plane 1/2...