Up-to-date information about all ongoing and planned work
Please update this list regularly! I think this will help all of us to keep a better overview of the whole project.
 Logbook 
 
-  29.09.2009 
-  Finished low voltage distribution for sector 3 plane 3&4 (Torsten)
-  Power Supplies installed (Torsten)
-  Connected sector 3 with a temporary "final" test setup (Kathrin, Jan)
 
-  02.10.2009 
-  Installation of main slow control network switch (Sergey, Jan)
 
-  07.10.2009 
-  Labeled optical cables for sector 6 (Torsten, Jan)
-  Network (VLAN & GSI network) connection on both mdc mounting places (Sergey, Jan)
-  Two additional (3 in total) FanPW v2 adjusted and tested (Jan)
-  Automatic OEP test script almost finished (Sergey)
 
-  08.10.2009  
-  09.10.2009 
-  Tested 15 more OEP, found some broken ones (Jan)
-  Enabled write protection on all 30 OEP finished (Cahit, Jan)
-  Labelled and Cut optical fibres for sector 5 (Kathrin, Jan)
-  Cut all power cables for one sector plane 3&4 (Kathrin, Jan)
-  Cut optical cables for two full sectors plane 3&4 (Kathrin, Jan)
 
-  12.10.2009 
-  Cut and tested power cables for two full sectors (Linda, Kathrin, Jan)
-  Installed 50 OEPs: Sector 4 Plane 3 & 4; one long side of sector 3 & 5, plane 3 & 4 (Tingting, Kathrin, Jan)
-  Cut all cables belonging to sector 4 plane 3&4 (Kathrin, Jan)
-  Tested 30 OEP (Sergey, Jan)
-  Prepared chambers to move in sector 4 (Kathrin, Tingting, Jan)
-  Rasnik connector box moved (Torsten + ?)
 
-  14.10.2009 
-  Mounted both chambers (sector 6) together (Torsten, Erwin, ?)
-  Installed all cables (Kathrin, Tingting, Erwin, Jan)
-  Installed all OEP (Kathrin, Tingting, Jan)
-  Logged all available serial numbers (Kathrin, Tingting, Erwin, Jan)
-  tested 21 OEP, produced 43 OEP (Jan / Helga, Albrecht)
-  build rack with fans for three Optical AddOns (Jan)
-  glued final optical connector sector 4 (Torsten)
 
-  15.10.2009 
-  connected both chambers of sector 6 to MDC AddOn (Tingting, Kathrin, Jan)
-  Basic communication and readout tests succesfull (Tingting, Kathrin, Jan)
-  Connected sector 4, plane 3 to power and AddOn (Sergey, Jan) - will be used by Sergey for software tests
 
-  19.10.2009 
-  Noise tests with sector 4 
-  cosmetic repairs on sector 6
 
-  20.10.2009  
-  Test of threshold settings and internal calibration on sector 6 -> all boards behave normal (Christian, Jan)
-  Found quite high noise on all voltages, needs further investigation
 
-  21.10.2009  
-  23.10.2009 
-  Tested about 60 OEP (Erik, Paul)
-  Installed proper grounding for sector 4
 
-  28.10.2009 
-  Tested 34 OEP (Erik)
-  Adjusted FanPW2 on sector 4 (Kathrin, Jan)
-  worked on analysis scripts (Kathrin, Jan)
 
-  29.10.2009 
-  Installed OEP and cables on second half of sector 5 (Erwin, Gosia)
-  Produced optical cables for one sector plane 3&4 (Gosia)
 
-  30.10.2009 
-  Noise measurement for proposed position of cables for MDC II (Kathrin)
-  mounted cables on plane 4, sector 2 right side (Gosia, Kathrin)
 
-  02.11.2009 
-  Started removing cables from plane 2 (Sasha, Sergey, Jan)
-  Cut missing power cables (Gosia)
-  Mounted connectors on power cables in mainframe (Torsten)
-  Produced OEPs (Helga)
 
-  03.11.2009 
-  Removed all cables from plane 2 (Sasha, Sergey)
-  Labelled optical cables for sector 3 (Gosia)
-  Mounted cables and some OEP on sector 2 (Torsten, Gosia)
-  Produced OEPs (Helga)      
 
-  04.11.2009 
-  Labelled optical cables for sector 2 (Gosia, Torsten)
-  Equipped both long sides of sector 2
-  Started preparing power cables (Sasha)
 
-  05.11.2009 
-  chambers 1, 3 and 5 of MDC II moved to Rich tent
-  Logged serial numbers of three chambers
-  Decided on strategy for placing FanPW and Power Cables
 
-  12.11.2009 
-  chambers 1, 3 and 5 of MDC II moved back to frustum
-  chambers 2, 4 and 6 moved to RICH tent
-  Logged serial numbers of three chambers
 
-  18.11.2009 
-  Finished testing off all six chambers of plane II (Jrn, Kathrin, Jan)
 
-  07.12.2009  
-  09.12.2009 
-  CMS cables found to be not crimped correctly - to be reworked!
 
-  10.12.2009  
-  11.12.2009 
-  Reworked CMS cables sector 3 & 5 and plane 2 (Gosia, Erwin)
-  Finished cables on sector 3 (plane 3/4)
-  Tested FanPW3 / found to be ok. Rest of boards can be produced (Paul, Erik, Jan)
 
-  22.12.2009 
-  Finished cabling on long sides of plane 2 (Kathrin, Jan)
-  Installed missing OEP / Replaced broken OEP on plane 2 (Kathrin, Jan)
 
 Upcoming 
 
-  Gosia and Tingting are available for 3 weeks (in total) in january, in the 1st, 3rd and 4th week
-  Big coordinated effort in january to test all chambers of plane 3/4, finish upgrading plane 1, preparing all cables in mainframe for plane 1/2...
  Other Tasks