Logbook

Installation: INNER planes

Task Plane 1/2 Sector 1 Plane 1/2 Sector 2 Plane 1/2 Sector 3 Plane 1/2 Sector 4 Plane 1/2 Sector 5 Plane 1/2 Sector 6
Threshold test
 
 
 
 
 
 
Calibration test
 
 
 
 
 
 
Check Low Voltage Connectors on FANPV
 
 
 
 
 
 
Check Low Voltage Connectors on OEPB
 
 
 
 
 
 
Check connections between OEPB and MB
 
 
 
 
 
 

Installation: OUTER planes

Task Plane 3/4 Sector 1 Plane 3/4 Sector 2 Plane 3/4 Sector 3 Plane 3/4 Sector 4 Plane 3/4 Sector 5 Plane 3/4 Sector 6
Threshold test
 
14-18 Feb
 
 
 
 
Calibration test
 
14-18 Feb
 
 
 
 
Check Low Voltage Connectors on FANPV
 
 
 
 
 
 
Check Low Voltage Connectors on OEPB
 
 
 
 
 
 
Check connections between OEPB and MB
 
 
 
 
 
 

Empty space: not yet done; Brown: temporarily done; Green: finished