MDC Upgrade - the final phase

Meetings

The first meeting of this working period will take place on Monday, 4.1.2010 at 10 a.m. in the upper counting house.

Plans & Schedules

The main tasks

  • Testing of all chambers
  • Cabling of plane 1
  • Install missing parts on all chambers (Cables, Optical Connectors, Low-Voltage)

Available people

  • Monday and later: Christian, Jörn, Gosia, Kathrin, Jan
  • Tuesday (about 2 or 3 days): Khaled, Erik, Paul
  • Wednesday and later: Tobias
  • Second Week: Torsten (wednesday), Erwin, Tingting

Timeschedule

Monday (4.1.) should be used to do as much planning as possible so that we can start "working" with all available people on tuesday.
  • Find best positions for FanPW on plane 1
  • Discuss the list of needed tests for each chamber. I prepared some tables in the wiki: TestLogBook
  • Start testing

On Tuesday, Khaled, Erik and Paul will join us.
  • Prepare all cables for plane 1
  • mount optical connectors to all accessible sectors
  • prepare one optical connector to simplify test setups

Other work

Other work that can be done by us with the help of the Werkstudenten if no MDC-work is available:
  • place optical cables along mainframe
  • finish cleaning up of piles of unsorted cables in the back part of the cave
  • help Andreas building holding structures for TRB-stacks
  • help Torsten laying LV-power cables

Testing chambers

  • we have two MDC AddOns and three FanPW available. This is two complete test setups to test two chamber independently in parallel.
  • two people should work together in testing one chamber
  • Besides cabling of plane 1, in-depth testing of all chambers has priority!

Bookkeeping

These pages have to be maintained!

Boards availability

  • OEP: Box with all tested OEP (around 430 boards in total) is available in the cave
  • FanPW: Rest of 28 boards should arrive end of next week, then have to be tested and adjusted - available around middle of the month
  • MDC AddOn: New MDC board design is on its ways - boards are most likely available end of March / start of April
  • Hub2: (used to connect several MDC boards to CTS): Boards will be sent back to producer for some reworks to be done. Should be available in 2 weeks.
  • CTS: Central trigger system - I didn't hear any news from Mareks design during the last month.

-- JanMichel - 01 Jan 2010
Topic revision: r1 - 01 Jan 2010, JanMichel
 
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Hades Wiki? Send feedback
Imprint (in German)
Privacy Policy (in German)